PROJECT MANAGEMENT · METHOD, NOT IMPROVISATION

A funded project is run on four numbers

Structure, time, cost, risk. Keep them under control and you reach the final payment; find out about them at the end and all you can do is write reports justifying the variances. Below are the instruments we run them with, not the words to describe them.

01StructureWBS and work packages
02Timeschedule and critical path
03Costbudget and earned value
04Riskregister and assessment matrix

The structure

WBS · WORK BREAKDOWN STRUCTURE

Before the calendar and before the budget, the work gets broken down. If an activity is not in the structure it does not exist: no owner, no cost, nothing to report.

PROJECT
WP 1Management and coordinationCROSS-CUTTING
  • project charter and scope
  • roles and responsibilities
  • monitoring and financial reporting
WP 2Analysis and requirements
  • state of the art and constraints
  • specifications and acceptance criteria
  • verification plan
WP 3Implementation
  • operational packages
  • deliverables to be released
  • in-process quality control
WP 4Validation and acceptance
  • tests and measurements
  • acceptance testing and sign-off
  • technical documentation
WP 5Communication and disseminationCROSS-CUTTING
  • communication plan
  • materials and channels
  • events and publications
The 100% rule. The sum of the packages must cover the whole project and nothing more: no activities outside the structure, no duplicates. Management and communication are cross-cutting: they run for the whole duration and have no time slot of their own. This is the check we run before writing a single date.

Time

SCHEDULE · CRITICAL PATH

Not all activities carry the same weight. The ones in red have no float: if they slip by a day, the project slips. Those are the ones we look at every week.

M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
Start-up and governance
CRITICAL
Detailed design
CRITICAL
Procurement
2 months float
Implementation
CRITICAL
Communication
cross-cutting
Acceptance and validation
CRITICAL
Reporting and final payment
CRITICAL
Start-up and governanceM1 - M2
Detailed designM3 - M5
ProcurementM4 - M6
ImplementationM6 - M9
CommunicationM2 - M11
Acceptance and validationM10 - M11
Reporting and final paymentM11 - M12
critical activity, zero float activity with float verifiable milestone status date
A reading scheme, not a real project. The red chain is the critical path: the longest sequence between start-up and final payment. Every milestone is a fact you can prove with a document, not a percentage stated out loud.

Cost

EARNED VALUE

"We have spent 60% of the budget" tells you nothing. The question is how much work has actually been produced with that money. Three curves answer at a glance.

0 100% PROGRESS TIME STATUS DATE planned value earned value actual cost
WORK PRODUCEDEVhow much work has been produced, measured on the deliverables accepted.
WORK PLANNEDPVhow much was planned by the status date in the approved plan.
SCHEDULE INDEXSPIbelow 1 the project is behind plan: you act immediately.
COST INDEXCPIbelow 1 the work costs more than planned: the estimate to complete is revised.
Why it matters. In the drawing the red cost curve runs above the green curve of work produced: more is being spent than is being achieved. This reading shows it at the status date, not at the end of the project, when there is nothing left to correct.

Risk

PROBABILITY · IMPACT MATRIX

A risk written in a register is a risk somebody is watching. Every entry has an owner, a threshold and a countermeasure decided in advance, not while it happens.

PROBABILITY
very high
high
R1
medium
R2
low
R3
very low
R4
negligibleminormoderatemajorcritical
IMPACT
  • R1Delay in permitting times. Countermeasure: parallel activities started early and applications filed with time to spare.
  • R2A critical supplier becomes unavailable. Countermeasure: a second qualified supplier in place before the order.
  • R3Cost found ineligible at reporting stage. Countermeasure: prior check in writing on every doubtful item.
  • R4Change of contact person in the partnership. Countermeasure: shared documentation and minutes, not knowledge held in people’s heads.
Five by five. Probability times impact: the red zone is not accepted, it is reduced. The risk register is updated at every monitoring report, not once at application stage.

What the client is left with

Documents, not meetings. Each of these is what an auditor or an authority needs in order to understand the state of the project without calling anyone.

Project charterScope, objectives, roles and responsibilities, approved.
WBS and work planStructure, packages, deliverables and acceptance criteria.
ScheduleActivities, dependencies, milestones and critical path.
Itemised budgetCosts by package and by eligible cost category.
Risk registerAssessment, owner, threshold and countermeasure.
Monitoring reportsProgress, indicators, variances and corrective actions.
Reporting fileSupporting documents, ordered and reconciled with the approved budget.
Close-outMinutes, accepted deliverables, final payment claim and lessons learned.
Do you have a project running and no idea whether it is late?
With the approved plan and the costs incurred to hand, the answer takes a few hours. If needed, we take the management over straight away.
Tell us about your project

For the list of completed and ongoing projects, and for any detailed information, please contact us: we will provide it directly.

Discover the other services

manage_search

Monitoring

sticky_note_2

Project activities

progettazione
insights

Management

card_travel

Project management

settings

Technical assistance

book

Training

Formazione
emoji_objects

Research, Development, Innovation Industrialization

Ricerca Sviluppo Innovazione Industrializzazione